INSTALLATION

Installation Process

23 / 27
INSTALLATION

Installation Process

From permit applications to final inspections, here's what happens behind the scenes to get your solar system approved and installed.

ORDER SUBMITTED

What Happens When You Submit Your Order

You're already matched with an installer when you create your account. When you submit your order, your project is automatically routed to them—and work begins immediately.

1

Instant Notification

Immediately

The moment you submit your order, your assigned installer is automatically notified and your project enters their active queue.

2

Welcome Call

Within 24 hours

Your installer reaches out to introduce themselves, answer questions, and schedule your site survey.

3

Site Survey

Within 1 week

A technician visits your home to verify roof condition, take measurements, and finalize your system design.

4

Permit Submission

After site survey

Your installer submits all required permits and begins the approval process with your city and utility company.

Track Everything in Your Customer Portal

From the moment you submit your order, you'll have 24/7 access to your personalized dashboard. Track permit status, schedule updates, message your installer, and view every milestone in real-time.

Real-time updates
Direct messaging
Document storage
Progress tracking
PERMITS & APPROVALS

The Permitting Process

Solar installations require approvals from multiple authorities. Don't worry—your installer handles all of this for you.

City/County Permits

1-4 weeks

Building permits ensure your solar installation meets local building codes and safety standards.

Structural engineering review
Electrical permit
Building department inspection
Final sign-off from inspector

Utility Approval

2-6 weeks

Your utility company needs to approve the interconnection of your solar system to the grid.

Net metering application
Interconnection agreement
Meter upgrade if needed
Permission to operate (PTO)

HOA Approval

1-3 weeks (if applicable)

If you have an HOA, they may need to approve your solar installation—though many states limit what HOAs can restrict.

Architectural review submission
Panel placement diagram
Equipment specifications
Most HOAs cannot deny solar

Typical Timeline

From signing your contract to turning on your system, here's what to expect.

Week 1

Site Survey

Installer visits your home to verify roof condition, take measurements, and finalize system design.

Week 2-3

Permit Submission

Engineering plans are drawn up and submitted to your city/county for building permits.

Week 3-6

Permit Approval

Permits are reviewed and approved. Timeline varies significantly by jurisdiction.

Week 6-7

Installation

Crew arrives to install racking, panels, inverter, and electrical components. Usually 1-3 days.

Week 7-8

Inspections

City inspector verifies installation meets code. Any issues are corrected immediately.

Week 8-12

Utility Approval

Utility reviews and approves interconnection. You receive Permission to Operate (PTO).

PTO Day

System On!

Flip the switch and start generating clean solar energy. Monitor production from your phone.

Don't Worry—We Handle It All

You don't need to call the city, file paperwork, or chase down permits. Your installer manages the entire process from start to finish.

Permit Applications
City Coordination
Utility Paperwork
HOA Submissions